The Assaluyeh Ethylene Plant Was Part Of The Kharg Olefin Complex Which In Accordance To NPC Resolution No. Sp 1-111/592 Dated 19 Mar 2006, The Ethylene Project Has Been Assigned To Morvarid Petrochemical Company.
The Plant’s Feed Shall Be Supplied From The Production Of Ethane From South Pars Plants For A Capacity Of 650t/y.
The Plant’s Production Capacity Is 500,000 t/y Of Ethylene Which Shall Be Injected Into The West Ethylene Pipe Line.
The Main Aim Of The Project Is To Generate Job Opportunities As Well As Know-How Transfer, Increase And Use Of Productivity From The National Capabilities, Economical Advantage, Hard Currency Earnings And Finally , Supplying The Feed For The West Ethylene Pipe-Line.

Project Name 5th Ethylene (Assalouyeh)
Location Second Phase Of Petrochemical Zone
Allocated Land For Process Area 4.3 Hectare
Allocated land for storage area 3.47 Hectare
Total allocated land 27/11 Hectare
Licensor TECHNIP
Basic engineering contractor TECHNIP
Detail engineering contractor NARGAN
Procurement contractor TECHNIP - NARGAN
Civil contractor KHATAMOL ANBIA (RAH SAHEL)
Erection contractor KHATAMOL ANBIA (DARYA SAHEL)
MC NAM AVARAN DELVAR Construction & Engineering Co.
Project Budget  Approved Million euro 207.1
Milyard rial 1084.9
Total (milyard rial) 3474
Project duration 57 months
Project effective date 17/01/2004
Detail engineering effective date 17/01/2005
Start of civil activities 21/04/2006
Forecasted date for end of project 21/09/2008
Feed 650000 Ton/Year Ethane From South Pars
Product 500000 Ton/Year Ethylene
Consumption West Ethylene Pipe Line / Export